Progress along Calle 13

By Azucena Mazon

There has been an 85% advance in paving and sidewalk work along Calle 13, which will be detained for a week during the upcoming Rocky Point Rally so that bikers can freely circulate along the street as has been the tradition.

Staff working on the road project confirm a layer of asphalt just along one block is needed in order to finish the project, which will be done following the rally scheduled to take place Nov. 7th – 10th.

The entrance to Calle 13 from Blvd. Juárez will be given a layer of asphalt to ensure bikes and cars can circulate without any problems.

The paving work along Calle 13, which is one of the main routes connecting with the hotel and resort area, forms part of a 40 million peso investment from federal funds that are also being put to work for the paving of Calle 12 and the boulevard that runs in front of the Convention Center.

Avance del 85% en la Calle 13

Por Azucena Mazon

Un avance del 85% es lo que se ha logrado de la pavimentación y banquetas  de la calle 13, cuya  obra  detendrán por una semana  para dar paso a que motociclistas  Rocky Point Rally circulen libremente por esta calle como tradicionalmente lo hacen.

Personal que labora en la obra de pavimentación confirmaron que para culminar el trabajo  falta solamente el asfaltado de una cuadra la cual terminarán una vez culmine el rally de motos el cual se llevará a cabo del 7 a 10 de noviembre.

Se indicó que para que motociclistas y automovilistas circulen sin problemas se acondicionará la entrada del Boulevard Juarez  a la calle 13  con una carpeta  de asfalto.

La obra de pavimentación que se realiza en la calle 13, una de las principales rúas que conecta con la zona hotelera forma parte de una inversión de 40 millones de pesos de recursos federales que también serán destinados para la pavimentación de la calle 12 y del bulevar que lleva  al Centro de Convenciones.